Quantitative Aptitude SSC CPO, SSC quantitative aptitude Free access now

Time and Work for SSC CPO | Concepts & Practice | SSC CPO Quantitative Aptitude

Build Time and Work accuracy for SSC CPO with concept clarity, key relations, exam-speed methods and approved practice.

Tailored for SSC CPO Quantitative Aptitude. 6 active practice questions. Related topics: Percentage, Profit and Loss, Simple Interest.

Free now Concept summary Key formulas Basic tricks Limited practice access
Premium later Detailed solutions Weak-area analytics
7 min read
Medium
Medium weightage
6 practice questions
Login to save progress and track weak areas Login Sign Up
Why students use this page

Learn the shortcut first, then solve with less confusion

This page is built to show the shortcut, the trap, and the faster solving route before you start clicking through questions.

Learn the shortcut

Understand the fastest pattern for this topic before you attempt full MCQs.

Avoid common traps

See where students commonly lose marks so you can eliminate bad options earlier.

Solve faster in exam

Apply one practical method before attempting MCQs and cut down hesitation.

Quick Summary Free

Time and Work at a glance

Time and Work revision for SSC CPO: understand the base rule, apply the correct formula or relation, check common traps, then practise with approved questions.

Concept

Core idea

Time and Work converts completion time into work rate. If a person completes a job in x days, one day's work is 1/x. Combined work is found by adding rates.

SSC CPO focus: Solve the core method first, then use the approved practice questions on this page to build exam-speed accuracy.

Short Notes

Fast revision notes

Time and Work revision rule: concept → formula/relation → one worked example → timed practice → error review.

Revision

Last-minute points

  • Core concept
  • Key formula/relation
  • Common trap
  • Approved practice
Formula Box Free

Formula / key facts

  • Rate = 1/Time
  • Combined rate = sum of individual rates
  • Combined time = 1/combined rate
Shortcut Zone Free

Tricks / shortcuts

For integer times, assume total work as their LCM to avoid fractions.

Memory Trick

Remember faster

For integer times, assume total work as their LCM to avoid fractions.

Next Step

Ready to practice this topic?

Solve topic-wise questions, measure accuracy, identify weak areas, and prepare for mock tests faster with a sharper revision flow.

  • Topic-wise practice built around this concept
  • Accuracy-focused repetition before full mocks
  • Weak-area clarity for smarter revision
  • Faster transition into timed tests
Free now

You can start learning here right away, explore formulas and tricks, and use the current limited practice flow before premium tools arrive.

Exam Tips

How to score with this topic

  • Read the exact requirement before choosing a shortcut.
  • Keep units, signs and percentage bases consistent.
  • Use the final few seconds to verify direction and magnitude.
Mistakes

Common traps to avoid

  • Using a memorised shortcut without checking its condition.
  • Skipping unit or base conversion.
  • Doing long arithmetic before identifying the underlying relation.
Solved Example

Step-by-step example

Practice example: A contractor completes four-ninths of a job in 8 days. At the same rate, how many days are needed for the whole job?

Solution: The whole job will take 18 days.

Practice Preview

Before you solve

  1. A and B can complete a job in 18 days and 24 days respectively. In how many days will they complete it together?
  2. A worker completes three-eighths of a task in 6 days. How many days will the whole task take at the same rate?
  3. A can complete a work in 18 days. B is 50% more efficient than A. In how many days can B complete the work?
Learn the shortcut first

Shortcut before you solve

Time and work gets easy when you stop thinking in total days and start thinking in daily work.

Featured shortcut

Convert each worker into one-day work, then add or subtract work rates.

Exam-use rule

Work done in 1 day = 1 / total days.

Use this in 3 seconds

Convert everyone into one-day work first, then combine rates.

Faster solving steps

Use this 4-step method before solving to keep your thinking fast and repeatable.

Step 1 Identify relation

Spot the pattern, relationship, or core idea first.

Step 2 Apply same pattern

Use the same rule instead of re-solving from scratch.

Step 3 Eliminate wrong options

Remove confusing choices before comparing the last few.

Step 4 Confirm final answer

Pick the option that matches the shortcut most cleanly.

Practice Questions

Start with the first 10 questions free, then unlock the rest with premium

Now apply the trick on real questions

Use the shortcut above before solving these questions

Convert each worker into one-day work, then add or subtract work rates.

Tip: If A finishes in 10 days, A does 1/10 of the work in one day.
Real exam shortcut before you solve

A can finish a work in 10 days. How much work does A complete in 1 day?

Step 1

Total work is taken as 1.

Step 2

A finishes 1/10 of the work each day.

Rule

Work done in 1 day = 1 / total days.

3-second trick

Convert everyone into one-day work first, then combine rates.

Trap to avoid

Do not add days directly when workers are working together.

Correct answer

1/10

Worked example

A can finish a work in 10 days. How much work does A complete in 1 day?

Thinking path
  • One full work is the standard unit.
  • 10 days means one-day work is 1/10.
  • This becomes the base for combined work questions.

Final answer: 1/10

Why this is fast: Daily work form makes partnership questions almost automatic.

Free now: first 10 questions Premium later: full solutions, advanced tricks, targeted practice
Q1 Medium

A can complete a work in 18 days. B is 50% more efficient than A. In how many days can B complete the work?

Concept type: Work rate per day Shortcut used: Convert each worker into one-day work, then add or subtract work rates. Quick hint: If A finishes in 10 days, A does 1/10 of the work in one day.
Quick idea: B completes the work in 12 days.
Q2 Medium

A worker completes three-eighths of a task in 6 days. How many days will the whole task take at the same rate?

Concept type: Work rate per day Shortcut used: Convert each worker into one-day work, then add or subtract work rates. Quick hint: If A finishes in 10 days, A does 1/10 of the work in one day.
Quick idea: The whole task will take 16 days.
Q3 Medium

A and B can complete a job in 18 days and 24 days respectively. In how many days will they complete it together?

Concept type: Work rate per day Shortcut used: Convert each worker into one-day work, then add or subtract work rates. Quick hint: If A finishes in 10 days, A does 1/10 of the work in one day.
Quick idea: They will complete the job in 72/7 days.
Q4 Medium

A contractor completes four-ninths of a job in 8 days. At the same rate, how many days are needed for the whole job?

Concept type: Work rate per day Shortcut used: Convert each worker into one-day work, then add or subtract work rates. Quick hint: If A finishes in 10 days, A does 1/10 of the work in one day.
Quick idea: The whole job will take 18 days.
Q5 Medium

A worker completes seven-fifteenths of a job in 14 days. How many days will the whole job take at the same rate?

Concept type: Work rate per day Shortcut used: Convert each worker into one-day work, then add or subtract work rates. Quick hint: If A finishes in 10 days, A does 1/10 of the work in one day.
Quick idea: The whole job will take 30 days.
Q6 Easy

In a Time and Work practice set, a student answers 18 questions correctly out of 24. What percentage is correct?

Concept type: Work rate per day Shortcut used: Convert each worker into one-day work, then add or subtract work rates. Quick hint: If A finishes in 10 days, A does 1/10 of the work in one day.
Quick idea: Correct percentage = 18/24 x 100 = 75%.
Premium Practice Premium

More topic-wise practice sets unlock after the free preview, along with deeper explanations and faster revision support.

Detailed solutions, weak-area targeting, and advanced question sets will appear here as part of the full learning tools.

Unlock to view full solution
Premium Access

Stop guessing. Start solving like a topper.

Get detailed solutions, exam shortcuts, and targeted practice.

  • Solve questions 2x faster in exams
  • Learn shortcut tricks used by toppers
  • Fix your weak areas automatically
  • Access full solution explanations (step-by-step)

Used by 1,000+ serious aspirants

Free access is limited to first 10 questions

Pricing Preview

Choose your plan

Pick the plan that matches your prep speed. Premium unlocks immediately after a successful payment.

Basic

CustomView plans

  • Full solutions
  • Topic practice
  • Weak area tracking
Get Started

Ultimate

CustomView plans

  • Everything in Pro
  • Full mock tests
  • Priority features
Get Started

Take this concept into timed practice

Move from concept clarity to exam speed with topic-wise questions and mock tests.

Premium Tools

Unlock full learning tools

A premium layer is planned for learners who want deeper guidance, richer feedback, and faster mock-test readiness. Nothing is locked here yet, but this shows what the fuller learning stack will include.

  • Detailed solutions for tougher practice sets
  • Audio tricks for quick revision sessions
  • Exam-wise shortcuts and smarter attempt strategy
  • Advanced topic tests with progression cues
  • Saved progress and deeper analytics
  • Weak-area recommendations after real practice
Premium preview

Designed as a soft-lock preview only for now. The page still renders normally, while this block explains what extra depth and speed premium learners will get later.

Free now Concept notes, formulas, tricks, and limited practice entry points
Premium later Full solutions, analytics, recommendations, and deeper test workflows
FAQ

Frequently asked questions

How should I revise Time and Work for SSC CPO?

Revise the core relation, solve one worked example, then attempt a short timed practice set.

Are these official PYQs?

No. Practice questions are labelled from ExamPrepWay's approved original/practice bank unless a verified official source is explicitly shown.